Quantifying costs of the productivity loss due to schedule changes in construction projects
| DC Field | Value | Language |
|---|---|---|
| dc.contributor.author | Lee, Jae-Seob | - |
| dc.date.accessioned | 2023-04-27T08:40:22Z | - |
| dc.date.available | 2023-04-27T08:40:22Z | - |
| dc.date.issued | 2023-02 | - |
| dc.identifier.issn | 0969-9988 | - |
| dc.identifier.issn | 1365-232X | - |
| dc.identifier.uri | https://scholarworks.dongguk.edu/handle/sw.dongguk/2079 | - |
| dc.description.abstract | Purpose The purpose of the paper is to develop a method to integrate the schedule-based analysis with a productivity-based analysis to prove and support the result of the damages calculation. Design/methodology/approach In this paper, a "cost and schedule impact integration" (CSI2) model is proposed to objectively show and estimate lost productivity due to changes in construction projects. Findings A schedule-based analysis to include separate tracking of change order costs can be used to predict productivity due to the delay and disruption; changes in construction projects almost always result in delay and disruption. However, the schedule-based analysis needs to be integrated with a productivity-based analysis to prove and support the result of the damages calculation. Practical implications The results of this study expand upon construction practices for proving and quantifying lost productivity due to changes in construction projects. Originality/value The contribution of the paper is summarized as the introduction of a "schedule impact analysis" into a "cost impact analysis" technique to assess the damages, as well as to demonstrate the labor productivity impact due to delay and disruption in construction projects. | - |
| dc.format.extent | 18 | - |
| dc.language | 영어 | - |
| dc.language.iso | ENG | - |
| dc.publisher | EMERALD GROUP PUBLISHING LTD | - |
| dc.title | Quantifying costs of the productivity loss due to schedule changes in construction projects | - |
| dc.type | Article | - |
| dc.publisher.location | 영국 | - |
| dc.identifier.doi | 10.1108/ECAM-07-2021-0571 | - |
| dc.identifier.scopusid | 2-s2.0-85116926078 | - |
| dc.identifier.wosid | 000708081500001 | - |
| dc.identifier.bibliographicCitation | Engineering, Construction and Architectural Management, v.30, no.1, pp 56 - 73 | - |
| dc.citation.title | Engineering, Construction and Architectural Management | - |
| dc.citation.volume | 30 | - |
| dc.citation.number | 1 | - |
| dc.citation.startPage | 56 | - |
| dc.citation.endPage | 73 | - |
| dc.type.docType | Article | - |
| dc.description.isOpenAccess | Y | - |
| dc.description.journalRegisteredClass | scie | - |
| dc.description.journalRegisteredClass | ssci | - |
| dc.description.journalRegisteredClass | scopus | - |
| dc.relation.journalResearchArea | Engineering | - |
| dc.relation.journalResearchArea | Business & Economics | - |
| dc.relation.journalWebOfScienceCategory | Engineering, Industrial | - |
| dc.relation.journalWebOfScienceCategory | Engineering, Civil | - |
| dc.relation.journalWebOfScienceCategory | Management | - |
| dc.subject.keywordPlus | LABOR PRODUCTIVITY | - |
| dc.subject.keywordPlus | IMPACT | - |
| dc.subject.keywordAuthor | Construction changes | - |
| dc.subject.keywordAuthor | Productivity loss | - |
| dc.subject.keywordAuthor | Damages | - |
| dc.subject.keywordAuthor | Delay | - |
| dc.subject.keywordAuthor | Disruption | - |
Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.
30, Pildong-ro 1-gil, Jung-gu, Seoul, 04620, Republic of Korea+82-2-2260-3114
Copyright(c) 2023 DONGGUK UNIVERSITY. ALL RIGHTS RESERVED.
Certain data included herein are derived from the © Web of Science of Clarivate Analytics. All rights reserved.
You may not copy or re-distribute this material in whole or in part without the prior written consent of Clarivate Analytics.